CDS-SL TRR1 for VBox production

Europe/Stockholm
France

France

Cryodiffusion, Lery, France
    • 08:30 08:45
      Executive session (CLOSED SESSION) 15m

      Review committee only

    • 08:45 09:00
      Introduction 15m
      Speaker: John G Weisend II (European Spallation Source ERIC)
    • 09:00 09:20
      CDS-SL production schedules 20m
    • 09:20 10:20
      CDS-SL VBox Verification Plans 1h
      • fabrication and factory acceptance test plans (30')
      • verification activities and procedures for welding works (30')
    • 10:20 10:35
      COFFEE BREAK 15m
    • 10:35 12:00
      CDS-SL VBox Verification Plans – cont. 1h 25m
      • verification activities and procedures related to pressure and leak tightness tests (30’)
      • verification activities and procedures for dimension control works (30’)
      • test equipment and supporting personnel (25’)
    • 12:00 13:00
      LUNCH 1h
    • 13:00 13:30
      Visit to the CDS-SL Vbox production hall 30m
    • 13:30 14:10
      Response to CDR Committees’ recommendations 40m
    • 14:10 15:00
      Discussions on: 50m

      PQPs (15’)
      RAMI and Safety Reports (20’)
      Project risks (15’)

    • 15:00 15:15
      COFFEE BREAK 15m
    • 15:15 16:00
      Discussion and questions 45m
      • factory tests and verification activities
      • project risks
      • ESS observation on CDS designs
      • etc.
    • 16:00 16:45
      Committee deliberations (CLOSED SESSION) 45m

      Review committee only

    • 16:45 17:15
      Recommendations and preliminary conclusions of the review 30m
      Speaker: John G Weisend II (European Spallation Source ERIC)