Minute of 22nd of September
Participants: K. Iakovidis, N. Gazis, P. Pierini, H. Przybilski, X. Roy,
The design of Version 2 is acceptable.
Henry: We have to make sure that the trolley is stable enough and to not be moving towards the cryo module. This we have to secure it by keeping the trolley stable. This could be done for the first time and to investigate if it is secure enough.
Keep in mind that we might need to do a third design with the pillars in the tunnel be in place. In that case we have to check the distance between the pillar and the cryo module and the height of the pillar.
The parts are shipped and will arrive to ESS on week number 39. Assembly of the trolley will start immediately after the receipt of the parts.
Some parts are givven for manufacturing in the workshop. No news about the delivery date. @Henry to talk with the workshop.