IRR for the Target Moderator Cryoplant
→
Europe/Stockholm
Tänkartanken (ESS)
Tänkartanken
ESS
Tunavägen 24 Lund
-
-
1
Executive session
-
2
Open the meeting and introductionSpeaker: Dr John G Weisend II (European Spallation Source ERIC)
-
3
Review of Compressor Hall PDR (Layouts) - by JOBSAB
-
4
Review of Installation plan - by JOBSAB
-
09:45
Break
-
5
Review of Hazard analysis (Installation)- by JOBSAB
-
6
Review of Compressor and Coldbox Placement - by JOBSAB
-
7
Review Work and Safety Coordination Plan - by JOBSAB
-
8
Review of electrical design and control system
-
12:00
Lunch
-
9
Review FAT results compressor delivery (Quality)
-
10
Review Commissioning Tasks/Schedule
-
11
Deliberations by review board
-
12
Recommendations and preliminary conclusions of the review
-
13
Close outSpeaker: Dr John G Weisend II (European Spallation Source ERIC)
-
14
AOB
-