Common Shielding Project
Thursday 24 Jan 2019, 09:00
→
17:00
Europe/Stockholm
Brightness (ESS HQ)
Brightness
ESS HQ
Odarslövsvägen 113 224 84 Lund
Charge and Agenda PDR common shielding -v4[1].docx
ESS-0472974 - System Requirements Specification for the Common Shielding System.pdf
ESS-0473697 - System Verification Plan for the Common Shielding System.pdf
ESS-0484542 - Preliminary Design Report.pdf
ESS-0513197 - Risk analysis for common shielding project PDR.pdf
Engineering Documents
ESS-0510203 - Guide Shielding D01-D03.PDF
ESS-0510213 - Guide Shielding E02.PDF
ESS-0510214 - Chopper Pit.PDF
Neutronics
ESS-0511498 - CommShield_TRandriamalala.pdf
ESS-0511500 - Prompt gamma shielding for the neutron guides at the ESS.pdf
ESS-0511504 - Florian-2019_01_10_ODIN_guide_shielding.pdf
ESS-0511506 - Simulating BIFROST instrument to 35 meters from source(1).pdf
ESS-0511508 - Shielding - dream and trex.pdf
ESS-0511510 - Simulating HEIMDAL beamline at the ESS.pdf
09:00
→
09:30
Introduction, Overview and Charge
Conveners
:
Ken Andersen
(
European Spallation Source ERIC
)
,
Zvonko Lazic
(
European Spallation Source ERIC
)
Andersen shielding PDR intro.pptx
09:30
→
10:00
Neutronics
Convener
:
Phillip Bentley
(
European Spallation Source ERIC
)
StandardShieldingPDR-Jan2019SML.pdf
10:00
→
10:30
Coffee break
30m
10:30
→
10:50
Engineering
Convener
:
Senad Kudumovic
(
European Spallation Source ERIC
)
Common Guide Shielding-SK.pptx
10:50
→
11:00
Installation
Convener
:
Antonio Bianchi
(
European Spallation Source ERIC
)
23_Shielding project PDR installation.pptx
11:00
→
11:20
Operations and Alignment
Convener
:
Ken Andersen
(
European Spallation Source ERIC
)
Andersen shielding PDR ops & risks.pptx
11:20
→
12:00
Discussion
12:00
→
13:00
Lunch
1h
13:00
→
14:30
Discussion
14:30
→
15:00
Coffee break
30m
15:00
→
16:30
Closed Session
16:30
→
17:00
Close-out