CDR for Test Stand 2 Personnel Safety System
Tuesday 9 Apr 2019, 13:00
→
18:00
Europe/Stockholm
Pacific Water (SEC) (ESS)
Pacific Water (SEC)
ESS
John G Weisend II
(
European Spallation Source ERIC
)
ESS-1083622 Charge.pdf
Committee discussion (closed)
1
PDR follow-up, SIL verification and updates on safety analysis
Speaker
:
Stuart Birch
(
European Spallation Source ERIC
)
Introduction_CDR_SLB_V3.pptx
2
Verification and validation plan for TS2 PSS
Speaker
:
Paulina Skog
(
OTIF AB (IBAN)
)
VV_for_TS2PSS.pptx
3
Updates on concepts of operation and system's architecture
Speaker
:
Morteza Mansouri
(
European Spallation Source ERIC
)
TS2 PSS_updates on concepts of operation and system's architecture_V03.pptx
4
Hardware integration and interfaces
Speakers
:
Morteza Mansouri
(
European Spallation Source ERIC
)
,
Mr
Peter Holgersson
(
ESS
)
TS2 PSS_hardware integration and interfaces_V02.pptx
5
TS2 PSS electrical and mechanical design
Speaker
:
Alberto Toral Diez
(
European Spallation Source ERIC
)
TS2 PSS electrical and mechanical design.pptx
TS2 PSS Rev2.pdf
15:00
Coffee break
6
Software requirements and software design
Speaker
:
Denis Paulic
(
European Spallation Source ERIC
)
TS2PSSCDR_SW_req_and_SW_design01.pptx
7
Progress on configuration management - ongoing work for TS2 PSS
Speaker
:
Meike Rönn
(
OTIF AB (IBAN)
)
8
Installation and commissioning plan
Speaker
:
Mr
Mattias Eriksson
TS2 CDR PSS.pptx
Committee deliberations (closed)
9
Closeout
Speaker
:
John G Weisend II
(
European Spallation Source ERIC
)