FREIA Tollgate 2 review
→
Europe/Stockholm
Tänkartanken (ESS Headquarters)
Tänkartanken
ESS Headquarters
1. FREIA Tollgate 2 Docs
- ESS-0110040-FREIA-TG2_Concept_of_Operations.docx
- ESS-0110041-FREIA-TG2_Systen_Requirements_Specification.docx
- ESS-0110045_FREIA-TG2_Preliminary_System_Design.docx
- ESS-0110046_FREIA-TG2_Work_package_specificaton.docx
- ESS-0110047-FREIA-TG2_Initial_Operations_and_Staging.docx
- Freia_motion_table_JBN121217_(ESS-0213010).xlsx
- Freia_PBS_v6.4_(ESS-0212972).pdf
- Freia_P&ID_v2.0_(ESS-0212989).pdf
3. FREIA Reference docs
- 20170705_FREIA_costing_and_delivery_for_Detectors.pdf
- Analysis_of_Shielding_Requirements_for_the_Freia_Instrument.pdf
- Chopper_options_FREIA__ESS_response.pdf
- ESS_Freia_Neutron_Chopper_Proposal_v1_Final.pdf
- ESS_Freia_Neutron_Guide_Proposal_Final_v1.pdf
- Freia-Fast_Slit_Project_Proposal_DRAFT_9_11_2017.pdf
- FREIA_scope-setting_meeting_summary_-v5.pdf
- FREIA_Scope_Setting_Report_updated_final.pdf
- MB_analysis_from_CRISP_PRELIMINARY.pdf
4. UK-ESS Project Management
- ESS-0114758_ISIS_Instrument_Design_Review_Process_.pdf
- ESS-0114760_ISIS-ESS-PM-PD-0001-Project_Management_Plan_v1.3.pdf
- ESS-0114761_ISIS-ESS-PM-PD-0009-Instrument_science_case.pdf
- ESS-0114762_ISIS-ESS-PM-PD-0010-Business_case.pdf
- ESS-0114763_ISIS-ESS-PM-PD-0012-ESS_instruments_Project_Board_Terms_of_Reference_V1.2.pdf
- ESS-0114764_ISIS-ESS-PM-PD-0014-ESS_Instrument_Project_Roles_and_responsibilities_V1.0.pdf
- ESS-0114766_P.M_2.0_Quality_plan_V1.1.pdf
- ESS-0114767_P.M_3.0_project_reporting_plan_V1.1_(requires_discussion).pdf
- ESS-0114768_P.M_4.0_Change_control_and_procedure_plan_V1.1.pdf
- ESS-0114769_P.M_5.0_ESS_staffing_and_procument_plan_V1.1.pdf
- ESS-0114770_P.M_6.0_Safety_Plan_V1.1.pdf
- ESS-0114771_P.M_7.0_Stakeholder_Plan_V1.1.pdf
- ESS-0114772_P.M_9.0_Risk_Plan_V1.1.pdf
- ESS-0114774_P.M_10.0_Cost_Plan_V1.1.pdf
- ESS-0114775_P.M_11.0_communications_plan_v1.1.pdf
- ESS-0114776_P.M_13.0_Critical_Success_Factor_v1.2.pdf
- ISIS-ESS-FREIA-Fi-0001_v1.0_Freia_TG2_costing_spreadsheet.xls
5. NSS Supporting docs
Reviews
- Andersen_FREIA_flux_calculation.pdf
- Andersen_review_of_FREIA_TG2_documents.pdf
- FREIA_TG2_Detectors.pdf
- MCAG_TG2_Review_FREIA_V2.pdf
- Neutron_Chopper_Systems_TG2_Review_FREIA_v1.pdf
- NOSG_FREIA_Shielding_Review.pdf
- Project_planning_TG2_Review_freia.pdf
- SEE_FREIA_TG2Checklist_181701_draft.docx
- TG2_FREIA_Optics.pdf
-
- 09:00 → 09:40
- 09:40 → 11:00
-
11:00
→
11:10
Coffee 10m
-
11:10
→
12:30
FREIA Team Presentations and Discussion
-
12:30
→
13:30
Lunch 1h
-
13:30
→
14:30
Internal Reviewer Presentations and Discussion
-
14:30
→
16:00
Closed session
-
16:00
→
16:30
Coffee 30m
-
16:30
→
18:00
Conclusions and summary